Description SES WATER Replace 100m of water main @ 12m per day, 2x transfers @ 1.5 per day, 1x final connection @ 3 days,... TRAFFIC MANAGEMENT TYPE = None / signing only
Location Entire length of Pebble Close from junction of Headley Common road... View on Map
Type ROADWORK
Delay Unknown
Diversion Route -
Diversion in force No
Planned start 10/12/2019 00:00
Planned end 23/01/2020 23:59