Description SES WATER Replace 540m of water main @ 12m per day, 19x transfers @ 1.5 per day, 3x final connections @ 3 days... TRAFFIC MANAGEMENT TYPE = None / signing only
Location From junction of Ashcombe Road to outside Lindens... View on Map
Type ROADWORK
Delay Moderate
Diversion Route -
Diversion in force No
Planned start 04/11/2019 00:00
Planned end 27/02/2020 23:59