Description SES WATER Replace 432m of water main @ 12m per day, 36x transfers @ 1.5 per day, 9x final connections @ 3 days... TRAFFIC MANAGEMENT TYPE = None / signing only
Location Bushfield Drive / Yeoman Way... View on Map
Type ROADWORK
Delay Moderate
Diversion Route -
Diversion in force No
Planned start 23/04/2019 00:00
Planned end 11/09/2019 23:59
Contractor SURREY