Description BT Build 1 precast chamber in 915mm x 445mm x 965mm deep in Footway,Install 2m of 1 way poly duct in F... TRAFFIC MANAGEMENT TYPE = None / signing only
Location OPP NO 8, STATION AVENUE... View on Map
Type ROADWORK
Delay Unknown
Diversion Route -
Diversion in force No
Planned start 02/12/2019 00:00
Planned end 04/12/2019 23:59
Contractor SURREY